is a zero waste turf project possible?
follow along on our journey to find out
Join Adam Coleman, VP of Marketing & Innovation for The Motz Group as he walks you through the journey of the Zero Waste turf replacement project. This is taking place at Mariemont High School in Cincinnati, Ohio. The reason this field was chosen was due to the school's original selections of sustainable components:
- Recycled Rubber Pad - Reusable
- Envirofill Turf Infill - Reusable
- Turf - Recyclable
Each week, The Motz Group will share a project update on this webpage and on our social media platforms. The latest updates will be at the top of the entries so if you just joined us in the middle of the project, we recommend scrolling all the way to the bottom to follow this project's story from the beginning.
WEEK EIGHT - FINAL UPDATE
zero waste turf project - week EIGHT
Adam Coleman returns to wrap up our #ZeroWasteWarrior project. The final touches of Envirofill turf infill are being installed and leveled out and the remaining leftover materials are being distributed to the proper recycling channels. A few items proved to be challenging to find homes for which resulted in less than one dumpster worth of waste. Follow along in this week's photo gallery to learn more details on those items.
- Envirofill originally used in the first field was reinstalled
- Less than one dumpster was needed over the course of the project
- Typically this job would take 10-20 dumpsters of waste to the landfill.
WEEK EIGHT VIDEO UPDATE
WEEK EIGHT PHOTO GALLERY
The final step if installation is infilling. The Motz team re-used the original Envirofill and installed it back into the new turf.
By Week 8, the replacement of Mariemont Highschool was substantially complete.
Rene Rodriguez, Field Superintendent and Adam Coleman, VP of Marketing & Innovation on site at the zero waste project
One area of waste the team struggled to find a home for was the glue buckets. The glue adhesive stuck to the plastic buckets did not allow for recycling.
A second material that was challenging to be 100% zero waste was the ends of the cardboard core pieces. The ends have plastic adhered to them making it difficult to separate the plastic and cardboard material which is needed for recycling.
The third material that did not find a perfect recycling solution was the rubber scraps from installing the re-used pad.
WEEK SEVEN UPDATE
zero waste turf project - week SEVEN
Joe Motz, Founder and CEO of The Motz Group visits the site of our Zero Waste project at Mariemont High School in Cincinnati to check out the progress and provide us with an update
- New turf has been installed and the crew is focusing on installing the logos and other cut-ins.
- Excess material separation has been a focus this week to prepare for recycling
- Leftover turf scraps will be used to make new nailer-board material
WEEK SEVEN VIDEO UPDATE
WEEK SEVEN PHOTO GALLERY
A Motz installation team member is seen here setting an inlay.
The Motz team members work together to install the end zone letters
Bags of plastic wrap and supersacks of turf scrap on site. The separation of materials is critical to enable recycling of each
The team delivered the excess plastic wrap from the Mariemont jobsite to Cincinnati Recycling and Reuse Hub. The plastic will be transferred to a affiliated facility in Indiana to be recycled into diesel fuel.
WEEK SIX UPDATE
zero waste turf project - week SIX
Adam Coleman returns with Peter Miller from BestPlus Lumber visiting the Mariemont High School project. This week, the installation crew worked on a system to easily separate waste stream materials as they built the project. Typically these materials would go straight to a dumpster.
- New turf is being installed this week
- Turf packaging and excess materials are being collected to be recycled
- BestPlus Lumber will collect the leftover turf material to up-cycle into plastic lumber
WEEK SIX VIDEO UPDATE
WEEK SIX PHOTO GALLERY
Turf rolls come delivered wrapped in plastic and with a cardboard core in the middle of the roll which are being collected for recycling.
When turf is installed, there are scraps created when each roll is cut to fit in place. These scraps are being collected for future up-cycling.
The turf scraps are all collected into super sacks so they avoid the landfill.
WEEK FIVE UPDATE
zero waste turf project - week FIVE
Adam Coleman returns to Mariemont High School's turf replacement project to check in on week five progress.
- The original shock pad was re-installed
- The installation team is staging the new rolls of turf
- Turf installation will begin this week
WEEK FIVE VIDEO UPDATE
WEEK FIVE PHOTO GALLERY
Shown here are rubber pad scraps - during installation, some cutting of the pad was necessary. We are brainstorming ways this can be used instead of wasted.
The repurposed pad has now been installed back down on the field.
The new turf rolls have arrived on site.
The "Zero Waste Warriors" aka the installation team
WEEKS THREE AND FOUR UPDATE
zero waste turf project - weeks three and four
Sarah Shewmaker, The Motz Group's Brand Manager, shares with us the update of week three and four of our Zero Waste Turf Project at Mariemont High School. During the third week, the focus was on the base. Once an old field is removed, the work needed on the base can vary. At Mariemont High School, it was in good shape so the base sub contractor wrapped up early with ensuring the base was ready to lay the re-used pad and new turf down. Week four, The Motz Group team finished prepping the field and started re-installing the pad.
- Week three was all about prepping the base for the new field
- The pad and infill are still on site waiting to be re-used
- Towards the end of week four, the pad will start to be re-installed
WEEKS THREE AND FOUR VIDEO UPDATE
WEEK THREE AND FOUR PHOTO GALLERY
The Motz Group team puts final touches on the base of the field during week four.
The reusable pad still sits on the track waiting to be re-installed while the field's base work is done.
The plywood boards allow equipment to move easily on and off the field.
The Motz Group finishes preparing the base during week four of the turf field replacement.
WEEK TWO UPDATE
zero waste turf project - week TWO
Adam returns to show you the progress from week one to week two. This week you can see the Envirofill removal has been complete, the turf has been removed and the pad has been removed leaving the field down to its gravel layer. Both the Envirofill and pad will remain on site to be reused in the new field.
- Field is down to gravel layer
- All turf has been pulled off, rolled up and most has been put on trucks to head to Georgia
- All the rubber pad is rolled up, labeled and organized and waiting to be re-used for the third lifecycle.
- Some of the supersacks of the Envirofill turf infill are at the end of the field waiting to be reused.
WEEK TWO VIDEO UPDATE
WHAT HAPPENS TO THE TURF?
REMOVING THE PAD
EXCESS INFILL LEFTOVER
WEEK TWO PHOTO GALLERY
The supersacks of Envirofill are moved off the field to wait for reuse.
Envirofill supersacks on the side of the field waiting for reuse.
Moving large amounts of supersacks filled with infill does not always happen seamlessly. One bag broke resulting in a loss of some of the reclaimed Envirofill.
It's common for some infill to pass through the turf perforations during the life of the field and during turf removal. The crew uses a leaf blower to move any excess leftover infill into the base so it is still not wasted.
The Motz Group field crew uses the TRS Wrangler with the Winder attachment to roll up each strip of the rubber pad. The technique for removing pad will depend on the type of pad originally installed.
The rubber pad rolls are moved off to the side of the field with the TRS's Wrangler machine with the Winder attachment.
The rubber pad rolls are now sitting on the side of the field waiting for reuse.
WEEK ONE UPDATE
zero waste turf project - week one
Usually on a turf field replacement, the turf is sliced up into 45" wide strips and rolled up with the infill still in the turf profile. For this special zero waste project, it was important that the infill is separated from the turf so it could be re-used for the new field. The crew started by removing the Envirofill from the turf. Envirofill has a 16-year warranty and can be reused for multiple turf life-cycles. It is also installed without any other infill materials, unlike most all other infills which allows for easier extraction and cleaner reuse. Once the Envirofill was removed, the next step was to slice the turf into the same 45" strips. The Motz Group uses machinery by Turf Reclamation Solutions to do the removal of infill and turf efficiently.
- Removed the Envirofill and placed in supersacks where it will stay onsite until it is time to reuse and install in the new turf
- Cut the turf into 45" strips, rolled each panel up and placed on trucks to be shipped to Georgia
- The turf will then be ground up to be recycled to make new pad for turf fields
WEEK ONE VIDEO UPDATE
CLOSE UP: TURF ROLLS
WEEK ONE PHOTO GALLERY
The field crew begins by detaching the turf from the outer edge nailerboard
Each nail is removed by hand by the field crew to prep the field for removing the main components: infill, turf and pad.
The turf is cut into 45" strips with the TRS Viper with minimal disturbance to the pad and base. Then the Rattlesnake (pictured here) is used to push the turf strips through and extract the infill directly into supersacks.
The supersacks are eventually moved off of the field to clear the surface for the turf removal.
The TRS Wrangler with the Winder attachment is used to roll the turf strips which allows for a more easily handled turf roll size.
The turf rolls are then ready to load into a truck. Usually they are disposed of in dumpsters and the landfill. These rolls will be heading to Georgia to be recycled.
What is zero waste?
According to the EPA, it is "the conservation of all resources by means of responsible production, consumption, reuse, and recovery of products, packaging, and materials without burning and with no discharges to land, water, or air that threaten the environment or human health.”